Subject : Description of my work on cs project from 12 to 19-10-2010

tuesday :
         4.30pm;
         * our group had a meet of around 1 hr.
         * discussed about project topics.
         
         10.00pm to 12.30 pm;
         * voting took place to decide the topic.
         * majority was towards doing "snake".
         * thought of various ideas to develop the game.

Wednesday :
           8.30 pm to 10.30;
           * I have learned the complete game procedure .
           * we discussed with out TA about our project.
           * our TA told to give our 2 nd and third choices.
           * we gave virus population and intel as our second and third preferences.
  
thursday :
           10.00pm to 11.00pm
           * i refered to c++ website to get an idea of the project.
           
saturday :
           10.00am to 12.00pm;
           * I studied Cohoon text book "EzWindows" chapter.
           * i made notes of some programmes.

sunday : 2.00pm to 5.00 pm;
          * our project was confirmed by our TA. 
          * i compiled the programmes uploaded on the website and wrote new ones(but failed in compiling).
          * we then divided the work accordingly.
          * our team got the work to take care of the fruit co-ordinates and snake's co-ordinates

monday : 10.00pm to 00.00 am
          * we started writing the programme.
          * i took care of documentation to be submitted(typing work).
          * i ve made sure that the functions(3) generated by my team mates are working properly.
          * made necessary corrections,suggested different ways.
  
wenesday : 8.30 pm to 11.00 pm
          * wrote a program on ezwindows but failed to compile
          * started writing a program to store the array values of the map 
          * made some test programs
          
saturday : 2.00pm to 4.15 pm
          * tried to complete the program but couldnt
          * discussed about various ways of writing the program
          * wrote some test programs
          
          5.30pm to 8.00pm
          * atlast my friend completed it
          * i did documentation work
          * wrote my dairy
          
sunday : 12.00pm to 12.45pm
         * explained my friend about the programs in cohoon about ezwindows
         
         2.00pm to 3.30
         * did some ezwindows stuff
         
         5.30pm to  7.30
         * got to know about the whole program
         * wrote peer reviews
         * did documentation work 